Sunday, June 7, 2009

Crossrail Stage

April 2009
May 2009
Jalan Lapang Station
Basement 1 complete, but the staircases is incomplete.
Tampines Primary School Station
Finishing torches with lighting being worked on.
Blk 157 Station
Underpass complete. Exit structures complete.
Bedok Reservoir Station
Basement 1 complete. There are plans to make way for jet grouting.
Western Police Division Station
Tunnel boring machine added.
Ashford Station
The concourse area is complete and the opening will be in December 2009.
The walkway (Ashford Walkway Tunnel) is closed.
Reinstatement works has been diverting the Ashford Timothy Line until June 2009.
Lorong Halus Station
Construction 'in fields'
Loyang Station
In excavation stage.
June 2009
Blk 157 Station
Construction begins on metal bars of the walkway to the Blk 157 Tram Stop.
Jalan Lapang Station
The staircases are complete, this is like Tanjong Pagar MRT Station. The escalators are taking shape. The structure is out of bounds, by using a barrier through it. FIRST STATION TO COMPLETE ITS STATION STRUCTURE
Tampines Primary School Station
Construction dig some soil to put a ventilation building similar to Bugis MRT Station.
Bedok Reservoir Station
Jet grouting has started.
Western Police Division Station
Road reinstatement has to be completed by July 2009.
Underpass to be completed by August 2009.
Ashford Station
Reinstatement of tracks has begun but station structure is incomplete.
Loyang Station
Digging concrete has started. Still in excavation stage.